Summary


  • This feature sets the target for quantity calculation.

How to Run


[Construction Mode]

  • Ribbon Menu > [Construction] Tab > [Quantity Table] Group > Generate

Explanation


Set the Quantity Generate

Sets the target for quantity calculation.

  • [Select Quantity Table]
    Create a new Quanity Calculation Table or select an existing Quantity Calculation Table.

  • [Classification]
    Enter the name of the Quanity Calculation Table.

  • [Select Target]
    Select the target for quantity calculation.

    • All : Select all created objects as targets for quantity calculation.

    • By Structure : Create the Quantity Calculation Table based on the structure classification system.

    • Construction Period : Set the corresponding target (Structure Classification System) and the specific construction period.

    • User Defined : Select only the desired objects as targets for quantity calculation.

 Detailed Explanation (By Structure)
  • Structure Table

    • Check : Select the target for quantity calculation using the On/Off setting.

    • Level / Name : Displays the settings defined in the Structure feature.

    • Template : Select the Quantity Calculation Template for that corresponding level.

 Detailed Explanation (Construction Period)
  • Date Setting : Set the date for the quantity calculation for a specific period of time. This can only be set for the ‘Construction Period'.

    • Off : Quantity is calculated without any time limit.

    • On : Desired period of time is set for quantity calculation.

The event must be defined using the Construction Task feature before the quantity can be calculated using the corresponding settings.

 Detailed Explanation (User Defined)
  • Target Unit Option : Set the unit for the quantity calculation.

    • Construction Mode : Unit in the Construction Mode is selected for quantity calculation.

    • Base Mode : Unit in the Base Mode is selected for quantity calculation.

    • Library Mode : Unit in the Library Mode is selected for quantity calculation.

Units used for quantity calculation in the Construction Mode is different of units used in Base Mode.

  • Concrete Member : Object unit / Pouring Part unit

  • Steel Member : Object unit

  • Rebar : Wire Body unit (The wire body unit cannot be used to calculate the quantity of couplers.)

  • Stiffener : Unit for individual stiffener

  • Tendon : Wire Body unit

  • Bolt : Bolt Group unit

  • Slope Solid : Soil Type unit

  • [Select Template]
    Create a new Quanity Calculation template or select an existing Quantity Calculation template.