What is a Work Type?

Related Function

Base Mode > Base > Property > Structure / Field

Type

Status
colourYellow
titleTip
,
Status
titleVerification
,
Status
colourGreen
titleExample

...

Therefore, CIM can make an aggregate table of quantity calculations for each material/material based on the model created.

...

Step 1. Work Type Configuration.

...

This is the setting method for calculating the quantity of the bridge substructure model in Figure. 1.

Base mode > Property > Work Type

Info

Base mode > Property > Work Type

Work Type is a tool that configures the quantity calculation form and sets the quantity calculation range system.

Click Work Type to go to the setup process for Structure and Field.

Info

Base mode > Property > Work Type > Structure

This tool creates a structural system for the quantity calculation form.

[This is the same as the sheet structure that is created in Excel.]

Info

Base mode > Property > Work Type > Field

This feature sets the Work Type and standard based on the object type that shows in the quantity calculation sheet.

...

Step 2. Describes the process used to enter the Structure of the Work Type.

...

  

...

Figure. 2 Structure Classification System

...

Info

The quantity calculation range of structures can be specified through the structure classification system in Figure 2. The classification system can be customized and input.

The example in the figure above was created based on bridge-substructure.

Level 1 – 1 Bridge Construction [This is Level 1 classification for bridge work.]

Level 2 - 1.1 Water Bridge [This is Level 2 classification for defining the bridge name.]

Level 3 - 1.1.1 Superstructure construction [This is Level 3 classification for the bridge structure, where a subsystem can be added.]

Level 3 - 1.1.2 Substructure construction [This is Level 3 classification for the bridge structure that can be entered into the structure property.]

Level 4 - 1.1.2.1 Starting Pier 1.1.2.1.1 Abutment body 1.1.2.1.2 Abutment wing

[This is Level 4 classification for the bridge structure subsystem.]

Level 4 - 1.1.2.3 Pier 1 1.1.2.3.1 Coping 1.1.2.3.2 Column, 1.1.2.3.3 Foundation

[This is Level 4 classification for the bridge structure subsystem.]

...

Step 3. Describes the process used to enter the Field of the Work Type.

The setting under Work Type > Field sets the quantity related construction type and standards using the model’s property information.

...

Figure. 3 Field Construction Structure (Concrete)

...

Info

If we take the Field Construction Structure (Concrete) in Figure 3. as an example,

  • Enter and select [ Strength / Material ]

In the concrete field, enter the name as ‘Strength’ and select ‘Material’ for the Field Type to use the material properties.

  • Enter and select [ Pour / User Defined ]

Enter the name as ‘Pouring’ and select ‘User Defined’ for the Field Type.

If ‘User Defined’ is selected, enter a name value (Ex. Concrete pump car pouring (0~15m)) under Items to add a tag in the quantity calculation.

...

Figure. 4 Field Construction Structure (Rebar)

...

Info

If we take the Field Construction Structure (Rebar) in Figure 4. as an example,

  • Enter and select [ Strength / Grade ]

In the rebar material field, enter the name as ‘Strength’ and select ‘Grade’ for the Field Type to use the rebar strength properties.

  • Enter and select [ Diameter / Diameter ]

In the rebar material field, enter the name as ‘Diameter’ and select ‘Diameter’ for the Field Type.

[Each rebar according to diameter is accounted for in the quantity calculation form.]

  • Enter and select [ Assembly Process / User Defined ]

If ‘User Defined’ is selected, enter the name of the item required for rebar assembly process.

...

Step 4. Describes the Material Settings.

...

For example, as shown in the figure above, the name of the concrete is changed and will be changed accordingly in the quantity calculation form.

...

Figure. 5 Material Settings (1)

...

Info

When entering the material as shown in Figure. 5,

① Select Tool Under Base mode > Property > Material .

② Select the Material Type on the left side of CIM. In the example above, Concrete Type is set.

...

Info

When entering the material as shown in Figure. 7,

④ Change the name value on the left side of CIM.

In the example above, 25-24-15 was entered for the Aggregate Dimension-Material Strength-Slump.

...

Step 5. Describes the process used to enter the quantity calculation property information into the CIM model using the animation below.

...